United States District Court,
N.D. California.
NISSAN FIRE AND MARINE INSURANCE COMPANY LTD.; Hitachi Data Systems Corp., Plaintiffs,
v.
BAX GLOBAL INC.; Cathay Pacific Airways, Ltd., Defendants.
No. C 02-2516 JSW.
May 12, 2009.
JEFFREY S. WHITE, District Judge.
Now before the Court are the cross-motions regarding damages and attorney’s fees filed by plaintiffs Hitachi Data Systems Corporation and Nissan Fire and Marine Insurance Co., Ltd. (“Plaintiffs”) and defendant Bax Global Inc. (“BAX”). The Court finds that this matter is appropriate for disposition without oral argument and it is hereby deemed submitted. See N.D. Civ. L.R. 7-1(b). Accordingly, the hearing set for May 15, 2009 is HEREBY VACATED. As the parties are familiar with the facts and procedural history of this case, there is no need to recite them here, except where useful in reaching the disposition.
This matter is currently before the Court on remand from the Ninth Circuit. On appeal, the Ninth Circuit held that the Warsaw Convention as modified by the Hague Protocol governs the issue of damages and that California choice of law rules determine the substantive law governing the issue of attorney’s fees. The Ninth Circuit remanded this matter to the Court to make the following two determinations: (1) whether, under the Hague Protocol, Hitachi is entitled to recovery, if so, the amount of the recovery; and (2) whether, under the relevant substantive law dictated by California choice of law, paragraph 16 of the waybill entitled either party to attorney’s fees. The Court will address each issue in turn.
A. Damages.
Under the Hague Protocol, Plaintiffs’ damages are limited to twenty dollars per kilogram. When the damaged portion of the shipment affects the value and usability of the other parts of the shipment, the damages are calculated based on the weight of all affected items in the shipment. Motorola, Inc. v. Federal Express Corp., 308 F.3d 995, 1001 (9th Cir.2002). The parties dispute what items within the shipment were affected by the damage to the disk controller unit.
Hitachi shipped 18 cartons of cargo on BAX air waybill No. CHG17066781 dated April 5, 2001 from Plainfield, Indiana to Hong Kong. (Stipulated Facts (“Stip.Fact”), No. 1; Trial Ex. 1.) The weight of the damaged carton and contents was 481 kilograms. (Stip.Fact, No. 12.)The damaged package contained a disk controller unit. (Id., No. 13.)The weight of a single Hitachi Data Systems 9960 is at most 1,062 kilograms when fully assembled.(Id., No. 14.)The weight of two Hitachi Data Systems 9960 Disk Subsystems is at most 2,124 kilograms. (Id., No. 15.)The entire shipment weighed 4,440 kilograms. (Trial Ex. 1.)
Plaintiffs’ witnesses testified that the 18 pieces of the shipment were built, configured, and tested to perform a single operating function for the customer in Hong Kong-to serve as the customer’s principal storage and remote backup storage of computerized data. These pieces were designed to operate together and could not operate for their designed function without all four disk controllers in proper operating condition. (Stipulated Testimony of Robert Shaffer, ¶¶ 1(a), 1(b); see also Stipulated Testimony of Kai Wah (Edwin) Chan, ¶¶ 2(a), 2(c).) The damage to the one disk controller prevented Hitachi from proceeding with the assembly of the parts in the 18 cartons into the storage and backup storage units. The damaged unit was returned, and the pieces in the other 17 cartons remained at the BAX Global facility at Hong Kong International Airport until a replacement for the damaged unit was received. (Chan’s Stipulated Testimony, ¶ 3(c).) BAX did not submit any evidence to contradict the evidence proffered by Plaintiffs’ witnesses, or otherwise contradict Plaintiffs’ showing that the other 17 cartons remained at BAX’s facility and could not have been assembled until the replacement disc controller was received. Therefore, the Court finds that the damage to the disk controller affected the value and usability of the other 17 cartons in the shipment. Accordingly, the Court will calculate the damages based on the weight of all affected items, which is 4,440 kilograms. BAX shall pay Plaintiffs $88,800 in damages.
B. Attorney’s Fees.
The parties concur that, under California law, Plaintiffs are entitled to attorney’s fees if they are the “prevailing party.” At issue is whether Plaintiffs qualify as the prevailing party. Under California law,
in deciding whether there is a “party prevailing on the contract,” the trial court is to compare the relief awarded on the contract claim or claims with the parties’ demands on those same claims and their litigation objectives as disclosed by the pleadings, trial briefs, opening statements, and similar sources. The prevailing party determination is to be made only upon final resolution of the contract claims and only by “a comparison of the extent to which each party ha[s] succeeded and failed to succeed in its contentions.”
Hsu v. Abbara, 9 Cal.4th 863, 876, 39 Cal.Rptr.2d 824, 891 P.2d 804 (1995) (citation omitted). Moreover, in determining the degree of litigation success, “courts should respect substance rather than form, and to this extent should be guided by “equitable considerations.” Id. at 877, 39 Cal.Rptr.2d 824, 891 P.2d 804. To illustrate, the court provided the following example: “a party who is denied direct relief on a claim may nonetheless be found to be a prevailing party if it is clear that the party has otherwise achieved its main litigation objective.”Id.
The Court finds in comparing the relative success of the parties on the contract claim, that Plaintiffs are the prevailing party. BAX seeks to limit the Court’s determination of whether Plaintiffs are the prevailing party to the issues litigated at the trial, as compared to the litigation of the entire case. The Court notes that BAX had persisted in contesting liability in a case management statement submitted one year after Plaintiffs initiated this action and after discovery had closed. Moreover, at trial, BAX contested where the damage occurred and thus challenged that the case was governed by the Warsaw Convention or the Hague Protocol. BAX eventually conceded liability and lost at trial on the issue of where the damage occurred. Although BAX did succeed in limiting the amount of damages and prejudgment interest allowed under the parties’ contract, the Court finds that the degree that Plaintiffs’ recovery was reduced does not, in balance, sufficiently undermine Plaintiffs’ success on their litigation objectives. Therefore, the Court finds that Plaintiffs are the prevailing party and, thus, are entitled to recover attorney’s fees.
C. Set-off.
In the Order setting forth the Court’s findings of facts and conclusions of law after the bench trial, the Court held that BAX was entitled to a set-off in the amount of the settlement paid by co-defendant, Cathay Pacific, to Plaintiffs, which was $15,000. Plaintiffs now argue that the BAX is not entitled to the set-off because Plaintiffs are not being fully compensated based on the Hague Protocol’s weight limitations on damages. However, Plaintiffs did not appeal the set-off issue to the Ninth Circuit. Therefore, the “rule of mandate” doctrine precludes the Court from addressing this issue on remand.
“The rule of mandate is similar to, but broader than, the law of the case doctrine.” United States v. Cote, 51 F.3d 178, 181 (9th Cir.1995). Upon receiving the mandate of an appellate court, a district court “cannot vary it or examine it for any other purpose than execution.”Id. (quoting In re Sanford Fork & Tool Co., 160 U.S. 247, 255, 16 S.Ct. 291, 40 L.Ed. 414 (1895)). Pursuant to the mandate rule, a district court cannot “revisit its already final determinations unless the mandate allowed it.”Id. The rule of mandate doctrine is jurisdictional. United States v. Thrasher, 483 F.3d 977, 982 (9th Cir.2007). The Ninth Circuit’s mandate directed this Court to determine Hitachi’s damages under the Hague Protocol and to determine whether either party was entitled to attorney’s fees. Therefore, the Court finds that it does not have jurisdiction pursuant to the “mandate rule” to consider the set-off issue.
CONCLUSION
For the foregoing reasons, the Court rules as follows on the parties’ cross-motions regarding damages and attorney’s fees:
(1) Plaintiffs are awarded $88,800 in damages;
(2) Plaintiffs are entitled to their reasonable attorney’s fees; and
(3) the Court does not have jurisdiction to consider the set-off issue.
IT IS SO ORDERED.